Planning · Facilitation script + register
Risk Analysis Workshop Kit
A 90-minute facilitation script with register and probability/impact scoring.
The problem it solves
Risks are known by individuals in the corridor and by nobody on paper.
How to run it
- 1Silent written brainstorm, 8 minutes, no discussion.
- 2Cluster into themes on a wall or board.
- 3Score probability and impact 1–5 each; multiply.
- 4Take the top five only: assign an owner and one concrete mitigation each.
- 5Schedule the re-score date before people leave the room.
What's inside
- Minute-by-minute facilitation script
- Risk register with scoring formula
- Prompt list of 30 common project risks
- Mitigation vs contingency guidance
Related downloads
Get this template
Sent as an editable document. No account, no drip sequence.
Want this facilitated with your team rather than filled in alone? I run these as a 90-minute session — free, no obligation.
Related templates
Work with me
Sometimes the fix needs a person, not a template.
I am Tigran Zakarian, a senior project manager with 13 years of end-to-end delivery for clients such as H&M Group, TV4, SEB and Clear Channel. I work on exactly the situations described across this site: rescuing drifting deliveries, setting up governance that people actually use, and facilitating the workshops that unblock decisions.
Projects & programmes
- Interim / rescue project management
- Programme & multi-team delivery ownership
- PMO, governance and steering setup
- Product ownership & backlog clarity
Workshops
- Risk analysis workshops
- Planning and prioritisation sessions
- Decision and stakeholder alignment
- Retrospectives that change something
Talks & training
- Educational talks and keynotes
- Hybrid PMBOK + Agile training
- Kanban / flow ways of working
- Team coaching for new PMs